Kīlauea roundabout being constructed on Kūhiō Highway
The Hawai‘i Department of Transportation (HDOT) is notifying drivers of a $12 million roundabout being constructed on Kūhiō Highway in Kilauea, which is planned to be completed late next year.
The roundabout is located at the intersection of Kalamania Road and Kolo Road.
According to a statement from the department, Kōloa contractor Goodfellow Brothers will be taking on the $12 million project which will have a new drainage system and improvements for pedestrians.
Construction began in May 2024 and is currently relocating utilities, potholing of the waterline, and installing a dust fence.
The roundabout is expected to be completed in December 2025.
Lane closures have not yet begun but updates will be posted on the Hawai‘i Department of Transportation website.
Sponsored Content
Notice: Function the_widget was called incorrectly. Widgets need to be registered using
register_widget()
, before they can be displayed. Please see Debugging in WordPress for more information. (This message was added in version 4.9.0.) in /mnt/efs/html/wp-includes/functions.php on line 6114